Overview
This article covers the steps required to roll back a schedule week within the Scheduling module.
If the portal does not have Scheduling and a week needs rolling back in the Rota module then please visit WFM - Rolling Back a Rota.
Rollback Steps
- From the side 'burger' menu, go to Scheduling > Administration > RollBack Rota
Please note: Ensure the 'Tronc/Tronc2' module is open before completing the schedule rollback in Labour Productivity. Please see the article WFM - Rolling back a Tronc Period in the Tronc2 Module which explains the rollback process for the Tronc and Tronc2 modules.
- Select the Location that needs rolling back
- Select the week in question from the Rota drop-down
- Select Rollback from the bottom-right corner
Fig.1 - Rolling back Labour Productivity schedule
The rota will then be rolled back.