  • Sam Spencer

    Hi Scott,

     

    I hope you are well.

     

    There is a setting in the user levels section, in scheduling:

     "Modify Schedule After Actual Signed Off"

    With this setting assigned to a user level, they will be able to make changes after the schedule is approved:

     

    Scheduling > Settings > User configuration > User levels > edit user level

    0
  • Scott Daley

    Hi Sam, 

     

    I have tried this and it doesn't work as you can still amend the schedule even after it has been approved.

     

    Scott 

    0
  • Debbie Thomas

    I was under the impression that  "Modify Schedule After Actual Signed Off" relates to Actualising the day.

    I don't believe there is a setting to stop the rota being amended after its been approved because it may need to be to reflect demand or staff changes, but there are reports to see Forecast v actual.

    0